Northlake Boulevard Construction in Palm Beach Gardens: Timeline

The project on Northlake Boulevard that will draw the most attention this month is the newest one. The I-95 interchange has a listed start of November 2026. The Beeline Highway end of the corridor has been under construction since March 18, 2024. At the other end, the Earman River bridge on U.S. 1 has been a work zone since February 10, 2025. Once the interchange starts, Northlake will have active state road work at its west end, its middle and its east end at the same time.

FDOT's posted dates show the corridor reopening in stages over three years, and the first stage is this winter.

The Calendar, End to End

These are the figures FDOT and the Palm Beach TPA have published as of late October 2026.

Project Location Listed cost Started Listed finish
Beeline Highway reconstruction Northlake to Blue Heron Boulevard $148.2 million March 18, 2024 Late 2029
I-95/Northlake interchange, contract T4666 Military Trail to Silverthorne Drive on Northlake $54 million November 2026, listed Late 2029
U.S. 1 roadway improvements 59th Street to Northlake $13.4 million August 27, 2025 Late 2027
Earman River bridge replacement U.S. 1, Northlake to north of Anchorage Drive $13.7 million February 10, 2025 Summer 2027 or Winter 2027

FDOT gives the Earman bridge two different finish dates. Its October 23 weekly traffic report says Summer 2027, and the project page says Winter 2027. Until FDOT reconciles them, treat the bridge's finish date as open.

The table shows the order. The two eastern projects finish in 2027. The two western projects run until late 2029. The stretch between Military Trail and I-95 has just been added to the schedule, so it is the last part of Northlake to reach the start of construction.

The West End Gets Its First Relief This Winter

The intersection of Beeline Highway and Northlake is being rebuilt as a partial continuous flow intersection. The broader project widens Beeline from four lanes to six between Northlake and Blue Heron Boulevard and replaces the Florida's Turnpike bridge over Beeline.

As of FDOT's October 23 to 30 traffic report, this is the daily setup at the intersection:

  • Northlake lanes are shifted at Beeline, and U-turns are unavailable in both directions. FDOT says this pattern stays in place until Winter 2026.
  • The northwest-bound Beeline ramp to eastbound Northlake is temporarily closed. Drivers continue on Beeline and turn right at the light to reach eastbound Northlake, and FDOT expects the ramp to reopen in Winter 2026.
  • On weekdays, Northlake east and west of Beeline can lose one lane in each direction, as needed, between 10:30 a.m. and 6 p.m.

So the first stage of relief on the corridor is two traffic movements coming back at the Beeline end, not a finished project. The reconstruction itself runs to late 2029. If the ramp and U-turns reopen when FDOT expects, that end of Northlake becomes easier to drive in the same season the interchange work gets going to the east.

The Middle: What T4666 Will Build, and What It Hasn't Announced

The interchange project covers 4.319 miles. On I-95, its limits run from south of Northlake to south of PGA Boulevard. On Northlake, they run from Military Trail to Silverthorne Drive. OHLA-USA is the contractor. According to the FDOT project page, the scope includes:

  1. Widening the I-95 exit ramps to Northlake and adding a wrong-way driving detection system
  2. Widening Northlake under I-95 to add a fourth through-lane
  3. Adding turn lanes and bike lanes along Northlake
  4. Milling and repaving both I-95 and Northlake
  5. Signal, ITS, drainage, lighting, signage and pavement marking upgrades

The November start date isn't fixed. FDOT's bid solicitation shows a letting date of May 20, 2026, a 120-day flexible start window and 929 contract days, so the first cones could appear somewhat after November. The project page doesn't yet list a phasing schedule or a closure plan. The bid's maintenance-of-traffic line items give some idea of what's coming: special detours with temporary pavement, a pedestrian and bicycle detour, 2,490 hours of traffic control officers and 23 business signs. FDOT's project page lists Meredith Cruz as the community outreach contact.

The case for the project rests on older numbers. FDOT's December 2016 interchange study counted 402 crashes at the interchange from 2010 through 2014, including two fatalities on the ramps. The same study projected that, without improvements, afternoon rush-hour drivers would face about three minutes of delay at each ramp signal by 2040. These figures are a decade old. They explain why the ramps are being widened and the wrong-way detection added. They don't describe today's traffic.

Local businesses sit inside the work limits. Colony Plaza, at 4265 Northlake Boulevard, is about 0.22 miles east of Military Trail. In June 2025, the City Council approved rezoning the 1.98-acre site and demolishing and rebuilding its 3,109-square-foot retail building. That puts a private rebuild and a state road project on the same block over roughly the same years.

The East End Finishes First

At the U.S. 1 end of Northlake, the Earman River bridge project is adding a second right-turn lane from southbound U.S. 1 onto westbound Northlake, along with bike lanes and new benches and planters for the Village of North Palm Beach. During construction, U.S. 1 between Anchorage Drive and Northlake has intermittent single-lane closures from 9:30 a.m. to 5 p.m. daily. The second turn lane matters most to drivers heading west from U.S. 1 toward I-95, since it feeds the stretch of Northlake the interchange project will be working on.

South of the bridge, the U.S. 1 roadway project from 59th Street to Northlake is adding bicycle lanes, new medians and LED lighting. For the week of October 25, it scheduled one inside or outside lane closure in each direction from 8 a.m. to 4:30 p.m. and again overnight from 9 p.m. to 7 a.m. Its listed finish is late 2027.

There's also new building on that corner. The Palm Beach Post reported on October 26 that Avalon Lake Park is nearing completion on the western nine acres of the former Twin City Mall site at U.S. 1 and Northlake. The seven-story building has 279 rental apartments. Leasing begins in November, with move-ins expected to start in January. The building opens while the bridge work beside it is in its final phase.

The Parallel Routes Have Their Own Status

Drivers will start comparing other ways to reach I-95. FDOT lists the I-95 ramp-safety project at PGA Boulevard as having started January 20, 2026, with a completion date of June 16, 2026. It added high-friction surface treatment to the ramps. The new I-95 interchange at Central Boulevard is still in final design. Its estimated cost is $113.3 million, and construction and completion dates are listed as TBD. Central Boulevard won't serve as an alternate route during the Northlake project's current schedule.

Off Northlake, Bike Projects Finish Before Any of the Road Work

The first projects to finish in this part of Palm Beach Gardens are bike projects, not road projects. The Palm Beach TPA lists the Burns Road separated two-way bicycle track, a 9.5-foot track from Military Trail to Alternate A1A, as under construction with an estimated completion of December 2026. The city's contract listing names JW Cheatham, LLC as the contractor, with an effective date of March 6, 2026 and a listed value of $1,533,503.

The Fairchild Avenue project from Fairchild Gardens Avenue to Campus Drive adds buffered bicycle lanes and an eight-foot path on the south side. The TPA puts its completion in Spring 2027. The city's listing names the same contractor, effective July 9, 2026.

Northlake will get bike lanes of its own under T4666, but on the late-2029 schedule. Burns Road should open about three years earlier. Weekly closure times change often, and FDOT posts updated Palm Beach County traffic reports through its District Four site.

If you own along this corridor and want to know how the construction timeline might affect the timing or pricing of a sale, Brad Ball can walk you through a valuation with the Beeline, I-95 and U.S. 1 schedules built in. Request a free home valuation, and we'll start with what's happening on your stretch of Northlake.

Experience the Difference

Whether you're buying your dream home or preparing to sell a luxury property, Brad and Shannon Ball provide personalized guidance backed by local expertise and proven strategy. Every recommendation is tailored to your goals, ensuring a seamless experience from consultation to closing. Let's make your next move a successful one together.